A 14.5 acre site containing 35 fully occupied apartment buildings presented a unique phasing and scheduling challenge.  The owner set a requirement that only one parking lot could be out of commission at a time, while installing a new site-wide storm water sewer system, removing and replacing 90% of the property's sidewalks and curbs, re-paving all of the parking lots, and reworking all entry poitns to the site, while also updating the landscaping, and installing new playgrounds.

PRECISE Project
www.precisecs.com
General Contracting

Parkway Gardens Apartments Sitework